Begin forwarded message:
From: "Carter, Chad" <Chad.Carter@Abilenetx.com>
Date: June 10, 2011 5:03:44 PM CDT
To: "Santee, Megan" <Megan.Santee@abilenetx.com>
Subject: RE: South 8th
Megan
A Phase 1 seal contract let and will go before City Council for resurfacing Amarillo, Meander, Vine, and Idlewild Streets from South 7th to South 11th. My hope is that this work will begin in August.
We are currently working on a Phase 2 contract for South 8th, South 10th, Jeanette, Peach, Palm, and Polpar. Those 6 streets are in worse condition than the Phase 1 streets and many of the intersections need extra attention to re-establish proper drainage. The Phase 2 project will include some curb and gutter replacement, pavement surface removal, an under-seal, and new hotmix surface. I hope to have the Phase 2 plans let to contract this summer, but construction will likely not begin until this fall.
The work was split into 2 phases because the seal coat has to be done in the summer months.
Chad
From: Santee, Megan
Sent: Friday, June 10, 2011 10:11 AM
To: Carter, Chad
Subject: Fwd: South 8th
Megan R. Santee
Sent from my iPhone
Begin forwarded message:From: "Dr. Lydia Long" <drlongbailey@yahoo.com>
Date: June 10, 2011 10:05:15 AM CDT
To: "Santee, Megan" <Megan.Santee@abilenetx.com>
Subject: RE: South 8thMegan, is this on the schedule soon?
Thank you, Lydia
Lydia M. Long, PhD.
Abilene Texas
325.676.4068
From: Santee, Megan [mailto:Megan.Santee@abilenetx.com]
Sent: Thursday, January 06, 2011 9:39 AM
To: 'Dr. Lydia Long'
Subject: RE: South 8th
Dr. Long,
Sorry for the delay but yesterday ended up quite hectic. We are fairly confident, of course in our line of work we always preface schedules with words like weather permitting and avoiding unforeseen circumstances, that the project on South 8th will be completed by the end of the summer. This allows us some room for foreseen conditions, like material delays or weather issues, or unforeseen conditions, like utilities or bid submittals, that might occur during the design, program or construct phases of this project. We are working on the design now. Then we will bid the contract and get Council approval. Then the work can begin. So, we would like to be conservative and estimate 6-9 months. Please let me know if you have any other questions.
Thank you,
Megan R. Santee, J.D.
Interim Director of Public Works
From: Dr. Lydia Long [mailto:drlongbailey@yahoo.com]
Sent: Tuesday, January 04, 2011 3:07 PM
To: Santee, Megan
Subject: RE: South 8th
Thank you!
Lydia M. Long, PhD.
Abilene Texas
325.676.4068
From: Santee, Megan [mailto:Megan.Santee@abilenetx.com]
Sent: Tuesday, January 04, 2011 1:48 PM
To: 'Dr. Lydia Long'
Subject: RE: South 8th
Dr. Long,
Chad and I are working on that and hope to have an answer to you by tomorrow afternoon.
Thanks,
Megan R. Santee, J.D.
Interim Director of Public Works
From: Dr. Lydia Long [mailto:drlongbailey@yahoo.com]
Sent: Monday, January 03, 2011 6:58 PM
To: Santee, Megan
Subject: South 8th
Thank you for the call today. I forgot to ask the timeframe for repairing South 8th, so I can tell others.
Happy New Year!
Lydia
Lydia M. Long, PhD.
Abilene Texas
325.676.4068