Plans for Sealing the Complex

Posted in: Hearthstone Manor
  • Avatar
  • oscar5381
  • Respected Neighbor
  • Brentwood, TN
  • 173 Posts
  • Respect-O-Meter: Respected Neighbor
All that I can say for sure is that Session Paving plans to start the resealing of the streets on Monday, July 9th. Right now, the Board has a tentative schedule, but I expect that it will be soon changed. Whenever the latest schedule is received, it shall be posted here.
  • Avatar
  • oscar5381
  • Respected Neighbor
  • Brentwood, TN
  • 173 Posts
  • Respect-O-Meter: Respected Neighbor
Unofficial paving schedule

Here's my unofficial schedule. When the schedule is firm, it'll be posted here. The Board is going to pass out notices to everybody. Be sure to read them. My schedule of paving is
Monday-July 9th
Tuesday-July 10th
Wednesday-July 11th
Friday-July 13th (maybe) Also, if it rains there won't be any paving that day.
One thing that I can tell you. Last year, I got tar on my running/walking shoes from the area that had had been resealed. I got the tar off be using a combination of water and Spray-N-Wash.
  • Avatar
  • oscar5381
  • Respected Neighbor
  • Brentwood, TN
  • 173 Posts
  • Respect-O-Meter: Respected Neighbor
Official Paving Schedule

Subject to change due to rain, the paving is scheduled to be on
Monday-July 9th
Tuesday-July 10th
Wednesday-July 11th
Friday-July 13th
Thursday the 12th is trash day, so no paving then. Let's all pray that there's no rain this week.:-)
  • Avatar
  • oscar5381
  • Respected Neighbor
  • Brentwood, TN
  • 173 Posts
  • Respect-O-Meter: Respected Neighbor
The Details of the Plan!!!!!!

Straight from the Board!!!!!
JUNE-JULY 2007

ROAD SEALING: IMPORTANT. Starting Monday, July 9th and ending Friday July 13th, unless there is rain, which will extend the project by a day for each day it rains. No work will be done on Thursday July 12, - garbage pick-up day. During this short term project, please be FLEXIBLE AND COOPERATIVE as streets will be down to one lane and will have to accommodate traffic in both directions. Work will begin at the entrance and cover half of the street for units 100 to 144, ending at the bridge. On Tuesday, July 10th they will seal the exit lane and the left hand lane from unit 100 to 144 ending at the bridge. On Wednesday, July 11th sealing will begin at the bridge and continue on the right hand side for units 200 to 246. No work will be done on Thursday, July 12th. On Friday, July 13th work will begin at the bridge and continue on the left hand side for units 200 to 246. PLEASE DO NOT DRIVE ACROSS WET SEALING. Park in visitor parking or a neighbor?’s driveway or leave you car in the garage if possible. Driving on wet sealant will track the black sealer onto your driveway and will reduce the coverage on the street. Traffic cones will be placed around wet sealer. PLEASE DO NOT MOVE CONES OR BARRIERS. Hearthstone Manor HOA and our contractor will not be responsible for any vehicle damage if it travels over new sealant that has been blocked off. This is an important project that will protect and extend the life of our streets - thank you for your cooperation. Information on this project is also posted on our website.
Advertise Here!

Promote Your Business or Product for $10/mo

istockphoto_12477899-big-head.jpg

For just $10/mo you can promote your business or product directly to nearby residents. Buy 12 months and save 50%!

Buynow