Utility Relocation Work in Phoenix for week end 2/5/2006
Line Section 1
Qwest will place conduits crossing 19th Ave @ Camelback. They will maintain 1 north and 1 south bound lane on 19th Ave and 1 west bound lane on Camelback. The crews will work from 7:00pm – 6:00am. The work should take about 2 weeks.
SWG will be lowering their gas main in the south bound lanes on 7th Ave, south of Camelback. They will maintain two lanes in each direction on 7th Ave from 7:00am – 4:00pm. The work should take 4 days. (New)
Line Section 2
SWG will begin lowering their gas main between Columbus – Virginia on Central. The crew will work from 8:30am – 4:00pm Monday – Saturday. 2 lanes each direction will be maintained on Central.
SWG will be lowering their gas main in the intersections of Thomas and Mc Dowell on Central. Two lanes will be maintained in all four directions between the hours of 8:30am – 4:00pm. The crews will work Monday – Saturday for about 6 weeks.
Willo Area: See above
Line Section 3
Qwest will begin lowering existing lines and relocate manholes on the west side of Central, between Van Buren - Adams. The crew will work in LS-3 24 hour closure. The work should be completed by January 31st.
SWG will begin lowering their gas main on Jefferson between 11th St – 15th St. Day crews will be working form 8:30am – 4:00pm and maintain 2 lanes on Washington. The work should take about 4 more weeks.
SWG will be removing their abandoned main on the west side of 1st Ave, from Monroe – Polk. The work is from 8:30am – 4:00pm, Monday – Saturday. The work should take about 2 weeks.
Line Section 4
APS is installing duct bank on Washington from 30th St – 36th St. The crew is working from 8:30 am – 4:00pm. 2 lanes in each direction will be maintained on Washington during construction. The work should take about 4 more weeks to complete.
APS will begin moving overhead 12Kv lines on the south side of Washington, between 38th St – 36th St. The work will be done between 7:00am – 4:00pm and require just an east bound curb lane closure. The work should take about 2 weeks.
Line Section Four’s contractor (SSWJV) will maintain one lane of traffic for east & west bound traffic on Washington from 42nd St – Mill Ave. The crew is placing sleeves for underground utilities and work from 7:00 pm – 6:00am.
Line Section Three’s contractor (Archer/Western) will restrict the north bound #1 & #2 lanes on Central for 3-4 months from Washington – Polk St. The closure will be a 24 hour restriction for underground wet utility relocation & underground structure reinforcements. Also, they are restricting the #1, & #2 lanes on Washington, between Central and 7th St. In addition, they are restricting the #1 & #2 lanes on 1st Ave, Jefferson – Fillmore. Washington and Jefferson are restricted to 2 lanes @ I-10. Lastly, they are working on APS’s overhead to underground conversions on Washington & Jefferson, between 25th St – 12th St.
Line Section Two’s contractor (Herzog) will be extending 1st Place to Monterey Way. Also, they are working in the north bound lanes on Central, north of Turney for water main relocation. Also working in the north bound lanes on Central, south of Indian School for sewer and storm drain relocation.
Line Section One’s contractor (Kiewit) will begin road widening and utility relocation on the south side of Camelback, west of Central. Also, on the west side of 19th Ave, north of Camelback for SRP irrigation relocation.
If you have any questions, please give me a call.
Bobby Wojciechowski
(602) 206-6554
Lisa,
Thanks for taking the time to speak with me concerning the gas line replacement project in the area of Central & Camelback. I met with our contractor, Northern Pipeline (NPL), to address the concerns of your residents. All of the issues have been addressed with the most notable changes being a new start time on weekends of 9am and all drivers on the job site have been instructed to minimize travel through the neighborhood and to keep engine noise and speed to a minimum. Any further complaints will result in the immediate removal of the offending person(s). I spoke with Mr. Jones on Friday 1/20 and relayed this to him as well. Mr. Jones asked that all future communication go through you on this project. Below you will find my contact information. Please do not hesitate to contact me for any issues or questions that arise during the remainder of our project.
Cell Phone 602 763 9015
Danny Rions
Supervisor/Central Arizona Construction
(602) 484-5438
danny.rions@swgas.com
Email us
lprocknow@valleymetro.org