Below, a list of projects that may have an impact on traffic in and around the Swan Lake neighborhood.
Information comes from the City of Tulsa website on Public Works Project Status Reports (http://www.tulsacouncil.org/news.php).
15th and Utica Intersection ?
Project No. 014100
?· Council District: 4
?· Funding Source: 2001 Sales Tax
?· Engineer: BKL, Inc.
?· Design Work: 100% complete
?· Contractor: N/A
?· Construction start: February 2007
?· Construction cost: N/A
?· Scheduled Completion date: December 2007
?· Work completed: 0%
?· Time expended: 0%
Status: Design is 100% complete and the rightofway
acquisition is complete. The original
construction start date of June 2006 was optimistic. As such, there has been a delay in the utility
rightofway
acquisitions? the construction start date is February 2007. We anticipate a December
2006 advertisement date.