Here is a list of various T-REX activities scheduled for next week----
* Feb 13-17 - There will be crews doing punch list work on the drainage system between Logan and Emerson on both sides Buchtel at night.
* Soundwall construction along NB I-25 between Franklin and Downing will continue
* Feb 14 - 18 - Denver Water will be doing work that requires them to reduce the lanes on University Blvd to 1 lane in each direction. They will be starting their work on the west side beginning at Jewell going north.
* Feb 21 - 25 - Denver Water will be working on S Buchtel on the north side. Traffic on Buchtel will continue to be 1 lane in each direction on the south side.
* Feb 26 & 27 - Denver Water will be closing Buchtel at University. Denver Water will be working on the west side and T-REX will be working on the east side. University Blvd will have 1 lane in each direction. Crews will attempt to have the intersection open by the evening for a DU basketball game.
* There will be various lane closures on I-25 at Colorado Blvd as crews begin reconstruction of the bridge.
* Feb 16 - Drainage work will begin at the intersection of Iliff and South Valley Highway. This work will require the closure of that intersection and the detour in that area will change slightly. This work will be done during the day.
* Feb 13 - There will be nighttime lane closures on NB I-25 at Yale and the Yale on-ramp to NB I-25 will be closed.
* Feb 12- The right lane of WB Hampden Ave will be closed on Saturday morning from 6 am until noon to prepare for the bridge deck pour scheduled for Sunday night. In addition, there will be only one left turn lane to take motorists from the Hampden Ave off-ramp from northbound I-25 onto westbound Hampden Avenue.
* Feb 13 - There will be a full closure of SB I-25 from Santa Fe to Hampden beginning at 9 pm for the bridge deck pour at Hampden Ave. There will be lane restrictions on NB I-25.
* Feb 13 - The right lane of WB Hampden Ave will be closed on Sunday night beginning at 8 pm for the bridge deck pour. In addition, there will only be one left turn lane to take motorists from the Hampden Ave off-ramp from northbound I-25 onto westbound Hampden Avenue. All lanes will be open by 5:30 am Monday morning.
* Feb 13 - There will be lane restrictions on SB I-225 and full closure at DTC from 1 am until 5:30 am. During the closure, traffic will exit and re-enter at DTC.
* Feb 17 - The SB I-225 ramp/tunnel to SB I-25 will open to two lanes through the tunnel. It will not be in final configuration as there is still work to be done. If there is bad weather that night it will be postponed until the night of Feb 20.
* Feb 13 - 17 - There will be various nighttime closures on the frontage road along NB I-225 between DTC and Yosemite.
* Feb 13 - 17 - Crews will be removing a small section of barrier along the outside of I-225 for a change order to provide access to LRT systems equipment. This work will be at night and may require lane closures on I-225.
* Feb 13 - Feb 17 - Orchard Rd and all of the ramps will be closed in both directions Sunday - Thursday nights from 9 pm until 5:30 am the next morning for landscaping -- During these overnight closures; motorists should use Greenwood Plaza Boulevard, Arapahoe Road and Yosemite Street as a detour for Orchard Rd and Belleview and Arapahoe for the ramps.
* Feb 14 - There will be nighttime lane closures on SB I-25 between Arapahoe and Dry Creek.
* Feb 13 - Feb 17 - There may be lane closures on Dry Creek Rd for landscaping.
* Throughout the week there will various lane closures on I-25 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com
Here is a list of various T-REX activities scheduled for next week----
* Jan 31 - The Colorado on-ramp to NB I-25 will be closed to move barrier from 9 pm until 5:30 am Monday morning. When the ramp opens on Monday it will be two lanes. Motorists should use University to access NB I-25.
* Now that the traffic has shifted on Colorado Blvd, the loop ramp from Colorado Blvd to SB I-25 is close. There is a temporary ramp on the east side of Colorado Blvd. NB Colorado Blvd motorists accessing SB I-25 turn RIGHT and SB Colorado Blvd motorists accessing SB I-25 turn LEFT.
* Jan 21 - Feb 3 - There will be various lane closures on I-25 at Colorado Blvd as crews begin reconstruction of the bridge.
* Jan 31 - The Evans off-ramp from NB I-25 will be closed overnight beginning at 9 pm for grading. Motorists should use Colorado to exit NB I-25
* Construction on soundwalls along SB I-225, on NB I-25 from Hampden to the Highline Canal, and on SB I-25 from Hampden to Quincy is continuing.
* Jan 31 - There will be lane closures beginning at 10 pm on SB I-25 at Yale for grading work. The Yale off-ramp from SB I-25 will also be closed.
* Jan 31 - The NB I-25 ramp to NB I-225 will be closed from 1 am until 5:30 am for bridge work. NB motorists should exit at Belleview; go east to DTC and north on DTC to NB I-225.
* Jan 21 - Feb 3 -There will be various lane closures on I-225 for grading and paving throughout the week.
* Jan 21 - Feb 3 - There will be nighttime closures on the frontage road between DTC and Yosemite for grading work.
* There may be lane restrictions on Belleview a couple of nights next week.
* Jan 21 - Feb 3 - Orchard Rd and all of the ramps will be closed in both directions on Sunday - Thursday nights from 9 pm until 5:30 am the next morning for landscaping -- During these overnight closures; motorists should use Greenwood Plaza Boulevard, Arapahoe Road and Yosemite Street as a detour for Orchard Rd and Belleview and Arapahoe for the ramps.
* Jan 21 - Feb 3 - There will lane closures on Dry Creek Rd for landscaping.
* Throughout the week there will various lane closures on I-25 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com
Here is a list of various T-REX activities scheduled for next week----
* Jan 24 & 25 - There will be a full closure of SB I-25 from Santa Fe to Hampden during the early morning hours of 1 am until 5:30 am for bridge work. Motorists will use the standard Santa Fe to Hampden detour.
* Jan 26-28 - There will be a full closure of NB I-25 from Hampden to Santa Fe during the early morning hours of 1 am until 5:30 am for bridge work. Motorists will use the standard Hampden to Santa Fe detour.
* Crews will be working along the east side of I-25 between Logan and University doing drainage and wall work and installing the center median high mast lighting.
* Jan 23 - The Broadway on-ramp to SB I-25 will be closed for wall work from 9 pm until 5:30 am Monday morning. Motorists should use Alameda to access SB I-25.
* Jan 23 - The University off-ramp from SB I-25 will be closed for paving from 9 pm until 5:30 am Monday morning. Motorists should use Colorado to exit SB I-25.
* Jan 23 - The Colorado on-ramp to NB I-25 will be closed for wall work from 9 pm until 5:30 am Monday morning. Motorists should use University to access NB I-25.
* Now that the traffic has shifted on Colorado Blvd, the loop ramp from Colorado Blvd to SB I-25 is close. There is a temporary ramp on the east side of Colorado Blvd. NB Colorado Blvd motorists accessing SB I-25 turn RIGHT and SB Colorado Blvd motorists accessing SB I-25 turn LEFT.
* There will be soundwall work along SB I-25 between Evans and Yale.
* Construction on soundwalls along SB I-225, on NB I-25 from Hampden to the Highline Canal, and on SB I-25 from Hampden to Quincy is continuing.
* Jan 23 - The NB I-25 ramp to NB I-225 will be closed from 1 am until 5:30 am for bridge work. NB motorists should exit at Belleview; go east to DTC and north on DTC to NB I-225.
* Jan 23 - 27 Orchard Rd and all of the ramps will be closed in both directions on Sunday - Thursday nights from 9 pm until 5:30 am the next morning for landscaping -- During these overnight closures; motorists should use Greenwood Plaza Boulevard, Arapahoe Road and Yosemite Street as a detour for Orchard Rd and Belleview and Arapahoe for the ramps.
* Jan 23 - 27 There will lane closures on Dry Creek Rd for landscaping.
* Throughout the week there will various lane closures on I-25 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com